Final Comments Due on Devil’s Gate ‘Big Dig’ Challenge

The deadline is today, Sept. 7, to submit comments regarding the recirculated portion of L.A. County’s Devil’s Gate Sediment Removal and Management Project plan. Still, opponents hope residents continue to contact officials with concerns about the project, which seeks to remove 2.4 million cubic yards of sediment from the reservoir.
The Arroyo Seco Foundation and the Pasadena Audubon Society filed a petition in court in 2014 challenging the Final Environmental Impact Report regarding what they call “The Big Dig.”
This April, L.A. Superior Court Judge James Chalfant temporarily halted the project and ruled that the Department of Public Works needed to modify its EIR before it could move forward with its plan, which is aimed at maintaining adequate downstream flood protection.
The judge asked the Flood Control District to provide evidence to support a 1-to-1 mitigation ratio in regard to biological resource impacts and that it find ways to reduce cumulative impacts.
Continue reading “Final Comments Due on Devil’s Gate ‘Big Dig’ Challenge”